Go-live Checklist

The go-live checklist and a cutover plan for launching a programme on Open Loyalty: readiness, the order of steps on the day, checks after the switch, and a fallback.

Go-live is when production configuration, migrated data and live channels come together. This page is the readiness checklist and cutover plan. Tell Open Loyalty your planned go-live date — and any change to it — early.

Readiness

Programme and configuration

Access and integration

Data

Capacity

People and communication

Cutover plan

1

Freeze

Stop changes on the old system (or put its earning into a holding state) so balances don't move during the migration.

2

Migrate

Run the final migration on production and reconcile counts and balances per wallet. Don't continue until the numbers match.

3

Activate

Activate the campaigns, rewards and challenges that were held back.

4

Switch the channels

Point the website, app, e-commerce platform and stores at the production integration. Switch webhooks on if they were held back.

5

Smoke test

With production test members: register, earn from a purchase and a custom event, see the balance, redeem a reward, receive the webhook in CRM. Remove or deactivate the test members afterwards.

6

Announce

Send the member communication and start marketing only after the smoke test passes.

Fallback

Decide before the day what happens if a step fails:

  • Before channels switch: stop, keep the old system running, fix and reschedule.

  • After channels switch: if earning is broken, keep the channels queuing events in the integration layer (they can be replayed thanks to stable document numbers and event IDs) rather than dropping them; fix forward.

After the switch

Watch closely for the first days — see After go-live.